SOFTSWISS Migrates Over One Million Players With Zero Data Loss in Under Five Hours

The company transferred approximately 100 TB of information to its Casino and Sportsbook platforms while preserving player records, existing passwords and the operator’s critical SEO structures.

SOFTSWISS, a global strategic partner for the iGaming industry, has completed the migration of more than one million players to its Casino Platform and Sportsbook with zero data loss. The project involved transferring approximately 100 TB of player data, with the final cutover to the new platforms completed in under five hours.

Based on this project, the company highlights three key considerations for operators planning a similar technology migration.

Approximately 100 TB of Data Transferred With Zero Loss

SOFTSWISS transferred approximately 100 TB of player data from third-party platforms to its SOFTSWISS Casino Platform and SOFTSWISS Sportsbook, without losing any information. This allowed the operator to retain its existing player records across both casino and sports betting operations on the new platforms.

The process begins with a discovery phase in which the SOFTSWISS team maps data, integrations, licences and payment systems. This assessment establishes the project’s scope and identifies technical dependencies before the switch, allowing the transfer to be planned around the operator’s existing infrastructure and requirements.

Existing Passwords and Critical SEO Structures Preserved

One of the key achievements of the migration was allowing players to retain their existing passwords and access their accounts on the new platforms without having to reset their credentials.

Maintaining this continuity of access helps reduce interruptions to player activity, potential lost betting revenue and additional customer support costs.

SOFTSWISS also preserved the operator’s critical SEO structures throughout the migration, maintaining the website elements that support its organic search visibility and rankings.

Preparing for a Controlled Transition

The final cutover to the new platforms was completed in under five hours. To achieve this, SOFTSWISS first carries out a build and testing phase, during which the Back Office, CMS, payment systems and content integrations are configured and tested in a staging environment.

A parallel run then mirrors live traffic across both systems. This allows the new platform to be evaluated under real operating conditions while the existing casino or sportsbook continues running as usual.

Before the final cutover, SOFTSWISS coordinates compliance sign-off with the client’s legal and compliance teams. This process covers licence continuity and GDPR/LGPD data transfer requirements, where applicable.

The operator retains its regulatory responsibilities, while the SOFTSWISS team remains on standby throughout the transition to support the process.

Kyryl Avdieienko, CPO at SOFTSWISS, highlighted the importance of preparation and testing in ensuring a successful migration:

“When a client trusts us with a migration, we approach every risk as if our own business were on the line. A fast cutover is only meaningful if the system is ready. Testing and a parallel run let our team assess the new environment with live traffic while the existing business keeps running. The decision to switch needs to rest on that evidence.

Our migration tools help preserve account access and support a seamless experience for players throughout the transition. Protecting the client’s data and day-to-day operations is what makes the move successful.”

Beyond the data transfer itself, SOFTSWISS allows operators to choose the products they need today and add further solutions as their businesses develop.

Companies considering a platform change can request a migration assessment from SOFTSWISS to understand the proposed timeline, technical dependencies and compliance checkpoints relevant to their operations.